eReM has build and delivered the necessary panels for the 150 kV station TenneT Middelharnis. These panels have been placed inside the station and outside in the field. Our installation department has taken care of the wiring. With the realization of this station it is possible to intercept the increasing amount of wind power in Goeree Overflakkee. The project has taken 6 months and was finished in the end of September 2017.
“A multidisciplinary project where our departments could join their forces.”
The delivery of a big amount of control panels for the Process Automation System (PAS) and the Vibration Monitoring System (VMS). View project